Northwest Construction
1 District 5 Crack Sealing Zoom To
Crack sealing and miscellaneous work on 121.33 miles of various roads in Transportation District 5 in Big Horn, Fremont, Hot Springs, Park & Washakie Counties.
Scheduled Completion: 6/30/10

Road Mileposts Delays Surface
WY 120 17 - 25 10 min. delays. Paved

Contractor Info
  • Hardrives Construction, Inc.
  • Billings, MT
  • (406) 245-3128
WYDOT Contact

Last Update: 12/17/09 6:49 AM
4 Cody - Powell, Cody Northeast Section Phase I Zoom To
Grading, draining, placing crushed base and bituminous pavement surfacing, removal dn replacement of bridges and guardrail, fencing, and miscellaneous work on 3.85 miles on US 14A beginning at RM 10.05 between Cody and Powell.
Scheduled Completion: 10/15/10

Road Mileposts Delays Surface
US 14 Alt. 10.055 - 13.9 Reduced speeds up to 30 MPH. Paved

Contractor Info
  • High Country Construction
  • Lander, WY
  • (307) 332-4933
WYDOT Contact

Last Update: 1/6/10 7:33 AM
5 District 5 Crack Sealing Zoom To
Crack sealing and miscellaneous work on 124.79 miles of various roads in Transportation District 5 in Big Horn, Fremont, Hot Spring, Park & Washakie Counties
Scheduled Completion: 6/30/10

Road Mileposts Delays Surface
US 26, US 287 98 - 110 10 min. delays. Paved

Contractor Info
  • Highway Improvement, Inc.
  • Sioux Falls, SD
  • (605) 371-1513
WYDOT Contact

Last Update: 1/19/10 8:44 AM
7 david test 1 Zoom To
David's testing...
Scheduled Completion: 3/12/10

Road Mileposts Delays Surface
US 26, US 287 1 - 2 No delays. Paved and Gravel

WYDOT Contact

Last Update: 3/10/10 2:56 PM
9 Cowley Streets Zoom To
Grading, draining, removal and replacement of surfacing, sidewalk, curb and gutter, placing crushed base and bituminous pavement surfacing, storm sewer system, landscaping, electrical systems, and misc. work on 1.5 miles of US 310
Scheduled Completion: 6/30/10

Road Mileposts Delays Surface
US 310, WY 789 241.5 - 243.14 No delays. Paved

Contractor Info
  • Reiman Corp.
  • Cheyenne, WY
  • (307) 632-8971
WYDOT Contact

Last Update: 1/13/10 10:11 AM
10 Basin-Greybull Zoom To
Level, overlay,chip seal, grading, draining, guardrail removal, and deer delineation
Scheduled Completion: 10/1/10

Road Mileposts Delays Surface
US 16, US 20, WY 789 196.75 - 202.7 No delays. Paved

Contractor Info
  • McGarvin - Moberly Construction
  • Worland, WY
  • (307) 347-4268
WYDOT Contact

Last Update: 1/13/10 10:10 AM
17 Steamboat Point Section Zoom To
Construction Winter Shut Down.
Scheduled Completion: 10/31/10

Road Mileposts Delays Surface
US 14 65.01 - 71.08 20 min. delays. Paved

WYDOT Contact

Last Update: 12/3/09 3:02 PM
19 Dell Creek Section Zoom To
Grading, draining, placing crushed base and plant mix pavement, bridge rehabilitation, guardrail, fencing and construction of retaining wall from the Bondurant Fire Hall to the mouth of Hoback Canyon.
Scheduled Completion: 6/30/11

Road Mileposts Delays Surface
US 189, US 191 142.6 - 147.7 10 min. delays. Paved

Contractor Info
  • E. H. Oftedal & Sons, Inc.
  • Miles City, MT
  • (406) 232-5911
WYDOT Contact

Last Update: 3/4/10 9:28 AM
Numbers by the projects refer to locations on the maps.